Project Management Professional (PMP) Exam Practice – Question0592

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:


A.
To the project management plan.
B. To the risk register.
C. In the scope verification processes.
D. And their impact to the project in terms of time, cost, and risk.

Correct Answer: D