Project Management Professional (PMP) Exam Practice – Question0606 Which of the following factors is lowest at the start of the project? A. Cost of changes B. Stakeholder influences C. Risk D. Uncertainty Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0605Project Management Professional (PMP) Exam Practice – Question0607