Project Management Professional (PMP) Exam Practice – Question0609

In which process might a project manager use risk reassessment as a tool and technique?


A.
Perform Qualitative Risk Analysis
B. Risk Control
C. Monitor and Control Project Work
D. Plan Risk Responses

Correct Answer: B