Project Management Professional (PMP) Exam Practice – Question0614

A method to manage stakeholder expectations in the scope statement is to clearly:


A.
state the guiding principles of the organization.
B. identify alternatives to generate different approaches.
C. state what is out of scope.
D. outline the results of the Delphi technique.

Correct Answer: C