Project Management Professional (PMP) Exam Practice – Question0617

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:


A.
Control Schedule.
B. Quality Control.
C. Perform Integrated Change Control.
D. Develop Schedule.

Correct Answer: A