Project Management Professional (PMP) Exam Practice – Question0621

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?


A.
Product scope description
B. Procurement statement of work
C. Project schedule
D. Work breakdown structure (WBS)

Correct Answer: B