Project Management Professional (PMP) Exam Practice – Question0625

Change request status updates are an output of which process?


A.
Perform Integrated Change Control
B. Direct and Manage Project Execution
C. Close Project or Phase
D. Monitor and Control Project Work

Correct Answer: A