The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
A. Determine Budget.
B. Baseline Budget.
C. Control Costs.
D. Estimate Costs.
A. Determine Budget.
B. Baseline Budget.
C. Control Costs.
D. Estimate Costs.