Project Management Professional (PMP) Exam Practice – Question0628

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:


A.
scope creep.
B. a change request.
C. work performance information.
D. deliverables.

Correct Answer: A