Project Management Professional (PMP) Exam Practice – Question0631 Which type of estimating is used to improve the accuracy of an activity's duration? A. Analogous B. Parametric C. Three-point D. What-if scenario analysis Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0630Project Management Professional (PMP) Exam Practice – Question0632