Project Management Professional (PMP) Exam Practice – Question0635

Which cost estimate technique includes contingencies to account for cost uncertainty?


A.
Vendor bid analysis
B. Three-point estimates
C. Parametric estimating
D. Reserve analysis

Correct Answer: D