Project Management Professional (PMP) Exam Practice – Question0640 The PV is $1000, EV is $2000, and AC is $1500. What is CPI? A. 1.33 B. 2 C. 0.75 D. 0.5 Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0639Project Management Professional (PMP) Exam Practice – Question0641