Project Management Professional (PMP) Exam Practice – Question0643

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?


A.
-8000
B. -2000
C. 2000
D. 8000

Correct Answer: B