Project Management Professional (PMP) Exam Practice – Question0645 Which tool or technique is used in Close Procurements? A. Contract plan B. Procurement plan C. Closure process D. Procurement audits Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question0644Project Management Professional (PMP) Exam Practice – Question0646