Project Management Professional (PMP) Exam Practice – Question0654

An input to the Estimate Activity Resources process is:


A.
Activity resource requirements.
B. Published estimating data.
C. Resource calendars.

D. Resource breakdown structure (RBS).

Correct Answer: C