Project Management Professional (PMP) Exam Practice – Question0658

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?


A.
$800
B. $1000
C. $1250
D. $1800

Correct Answer: A