Project Management Professional (PMP) Exam Practice – Question0672 Which of the following can be used as an input for Define Scope? A. Product analysis B. Project charter C. Scope baseline D. Project scope statement Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0671Project Management Professional (PMP) Exam Practice – Question0673