A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
A. Manage Stakeholder Expectations.
B. Monitor and Control Risks.
C. Plan Risk Management.
D. Report Performance.
A. Manage Stakeholder Expectations.
B. Monitor and Control Risks.
C. Plan Risk Management.
D. Report Performance.