Project Management Professional (PMP) Exam Practice – Question0681 What are assigned risk ratings based upon? A. Root cause analysis B. Assessed probability and impact C. Expert judgment D. Risk Identification Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0680Project Management Professional (PMP) Exam Practice – Question0682