Project Management Professional (PMP) Exam Practice – Question0687

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?


A.
Perform Quality Control

B. Quality Policy
C. Perform Quality Assurance
D. Quality Planning

Correct Answer: C