Project Management Professional (PMP) Exam Practice – Question0690 How is scheduled variance calculated using the earned value technique? A. EV less AC B. AC less PV C. EV less PV D. AC less EV Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0689Project Management Professional (PMP) Exam Practice – Question0691