Project Management Professional (PMP) Exam Practice – Question0693

Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?


A.
Risk analysis
B. Risk tolerance
C. Risk management
D. Risk attitude

Correct Answer: B