Project Management Professional (PMP) Exam Practice – Question0694

Quality and credibility of the qualitative risk analysis process requires that different levels of the risks probabilities and impacts be defined is the definition of what?


A.
Risk breakdown structure (RBS)
B. Risk probability and impact
C. Qualitative risk analysis
D. Risk response planning

Correct Answer: B