Project Management Professional (PMP) Exam Practice – Question0696 Which of the following is a component of three-point estimates? A. Probabilistic B. Most likely C. Expected D. Anticipated Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0695Project Management Professional (PMP) Exam Practice – Question0697