Inputs to the Define Activities process include:


A.
Project scope statement, resource calendars, and work performance information.
B. Scope baseline, enterprise environmental factors, and organizational process assets.
C. Project scope statement, approved change requests, and WBS dictionary.
D. Scope baseline, enterprise environmental factors, and activity duration estimates.

Correct Answer: B