Project Management Professional (PMP) Exam Practice – Question0702

The Plan Procurements process includes documenting project purchasing decisions and what other steps?


A.
Specifying the approach and identifying potential sellers
B. Specifying the approach and selecting a seller
C. Identifying potential sellers and obtaining seller responses
D. Specifying the approach and managing procurement relationships

Correct Answer: A