Project Management Professional (PMP) Exam Practice – Question0703 An imposed date for completion of the project by the customer is an example of a project: A. deliverable B. assumption C. constraint D. exclusion Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0702Project Management Professional (PMP) Exam Practice – Question0704