Project Management Professional (PMP) Exam Practice – Question0706

Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?


A.
-8000
B. -2000
C. 2000
D. 8000

Correct Answer: B