Project Management Professional (PMP) Exam Practice – Question0706 Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV? A. -8000 B. -2000 C. 2000 D. 8000 Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0705Project Management Professional (PMP) Exam Practice – Question0707