Project Management Professional (PMP) Exam Practice – Question0714

Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?


A.
Earned value performance
B. Trend analysis
C. Cost-benefit analysis
D. Variance analysis

Correct Answer: B