Project Management Professional (PMP) Exam Practice – Question0725

Overlooking negative stakeholders can result in a/an:


A.
decreased likelihood of conflicting interests between stakeholders.
B. decreased likelihood of the projects progress being impeded.
C. increased likelihood of project failure.
D. increased likelihood of project success.

Correct Answer: C