Project Management Professional (PMP) Exam Practice – Question0733

The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan is known as:


A.
Initiating.
B. Planning.
C. Executing.
D. Monitoring and Controlling.

Correct Answer: C