Project Management Professional (PMP) Exam Practice – Question0735

Projects can intersect with an organizations operations at various points during the product life cycle such as:


A.
When there is an operations shutdown (i.e. a strike).
B. When developing new products, upgrading products, or expanding outputs.
C. When a project transitions from a temporary to a permanent status.
D. When the project manager is promoted to operations manager.

Correct Answer: B