Project Management Professional (PMP) Exam Practice – Question0736 What is the lowest level in the Work Breakdown Structure called? A. Work Packages B. Activities C. Schedules D. Tasks Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0735Project Management Professional (PMP) Exam Practice – Question0737