Project Management Professional (PMP) Exam Practice – Question0739

The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:


A.
interview technique
B. information gathering technique
C. Delphi technique
D. feedback technique

Correct Answer: C