Project Management Professional (PMP) Exam Practice – Question0740 Which of the following is an input of the Define Activities process? A. Scope baseline B. Milestone list C. Resource calendars D. Activity list Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0739Project Management Professional (PMP) Exam Practice – Question0741