Project Management Professional (PMP) Exam Practice – Question0742

Project management processes are:


A.
Static; they must not change across different projects.
B. Applied globally and across all industry groups.
C. Discrete elements with well-defined interfaces.
D. Project phases, applied as required in different projects.

Correct Answer: B