Issue change requests and adapt approved changes into the projects scope, plans, and environment is an activity included in which of the following project management processes?
A. Direct and Manage Project Execution
B. Monitor and Control Project Work
C. Perform Integrated Change Control
D. Monitor and Control Risks
A. Direct and Manage Project Execution
B. Monitor and Control Project Work
C. Perform Integrated Change Control
D. Monitor and Control Risks