Which of the following is a schematic display of the projects schedule activities and the logical relationships among them?
A. Gantt chart
B. Project schedule network diagram
C. Project milestone list
D. Activity list
A. Gantt chart
B. Project schedule network diagram
C. Project milestone list
D. Activity list