Project Management Professional (PMP) Exam Practice – Question0749

The run chart created during the Perform Quality Control process on a project is used to show the:


A.
relationship between two variables
B. data points plotted in the order in which they occur
C. most common cause of problems in a process
D. frequency of occurrence

Correct Answer: B