Project Management Professional (PMP) Exam Practice – Question0751

Within project integration management, the statement of work (SOW) references which aspects of the project?


A.
Strategic plan, business need, and product scope description
B. Contract, enterprise environmental factors, and organizational process assets
C. Business plan, project management plan, and project schedule
D. Product lifecycle, business objective, and management strategy

Correct Answer: A