Project Management Professional (PMP) Exam Practice – Question0754

Which characteristic is unique to project work and does not apply to operational work?


A.
Performed by individuals
B. Limited by constraints
C. Temporary
D. Performed to achieve organizational objectives

Correct Answer: C