Project Management Professional (PMP) Exam Practice – Question0759

During a bridge construction project, a project manager discovers that one of the suppliers is the subject of a political issue. This could negatively impact the project.
What should the project manager do next?


A.
Inform the supplier that they are no longer able to work with them.
B. Initiate a seller selection process to find a replacement for the supplier.
C. Escalate the issue to upper management

D. Analyze the potential consequences.

Correct Answer: D