Project Management Professional (PMP) Exam Practice – Question0762

A project manager learns that the accounting department will not accept a new software product if it is unable to provide a specific report. Although this specific report was not included in planning, the developers say that it can be quickly implemented.
What should the project manager do?


A.
Have the developers design and implement the report.
B. Explain that the product will be included in the next project.
C. Add the report demand to the issue log.
D. Initiate the change request process.

Correct Answer: D