Project Management Professional (PMP) Exam Practice – Question0765

During a large projects execution phase, the business owner submits an approved change that will impact different business areas. During implementation, the project manager discovers that a key stakeholder failed to be engaged with this request. This key
stakeholder claims that the change will affect their business area.

What should the project manager do?


A.
Pause implementation of the approved change
B. Conduct an impact analysis session with the key stakeholder.
C. Resubmit the change request to the change control board (CCB).
D. Adjust the project manager plan to accommodate the change.

Correct Answer: B