Project Management Professional (PMP) Exam Practice – Question0766

A new project manager resumes a project in its execution phase. During a project status meeting, a team member reports an issue shared by a stakeholder.
What should the new project manager do?


A.
Review the issue log.
B. Advise the project team to immediately address the issue.
C. Review the stakeholder engagement plan.
D. Update the risk management plan

Correct Answer: A