Project Management Professional (PMP) Exam Practice – Question0767

A project that is on target is audited before closure of the execution phase, and one of the points addressed by the auditors is missing documentation. The project manager asks the team the reason for this, and learns that they had insufficient time to prepare it.
What should the project manager have done to prevent this?


A.
Requested a scope reduction so that the team had time to prepare the documentation
B. Requested additional resources to help prepare the documentation
C. Completed checks during the quality management process
D. Updated the risk register with this as a risk

Correct Answer: B