Project Management Professional (PMP) Exam Practice – Question0768

During project execution, a risk logged in the risk management plan as one with a very low probability occurs. The project manager needs additional time to deal with the risk:
What should the project manager do to obtain the additional time?


A.
Ask the sponsor for a schedule change.
B. Use the contingency reserve.
C. Eliminate some quality assurance activities.
D. Crash the schedule.

Correct Answer: B