During the execution of a large project across multiple domains, an identified risk is realized. What should the project manager do next?
A. Refer to the risk impact on the risk register and avoid the risk.
B. Plan a new risk response and update the risk register.
C. Refer to the project management plan.
D. Perform qualitative and/or quantitative risk analyses.