Project Management Professional (PMP) Exam Practice – Question0775

During a projects execution phase, two key business stakeholders request additional requirements be made within the same timeframe. Due to limited project resources and budget, the project manager cannot fully meet the expectations of these stakeholders.
Which of the following techniques should the project manager adopt to obtain support from both of these key stakeholders?


A.
Smooth/accommodate
B. Force/direct
C. Withdraw/avoid
D. Compromise/reconcile

Correct Answer: D