Project Management Professional (PMP) Exam Practice – Question0777

An international project team consists of local and overseas team members. The local team is responsible for integrating the projects work outputs. During the first integration phase, the need for a pre-validation of work outputs is identified, which will impact the
projects cost and schedule.

What should the project manager do next?


A.
Perform a root cause analysis of the work outputs.
B. Update the responsibility assignment matrix (RAM).
C. Issue a change request to update the project management plan.
D. Update the work breakdown structure (WBS) to include the pre-validation activities.

Correct Answer: D